After working with Digital Realty Trust for several months, we have finally received the contract so we can begin the electrical build-out for our next 25 cabinets. With it taking 3 weeks or so for the build out, we should be opening up the additional cabinet space in early July. In addition, we have received all the bids for the electrical work and it appears likely that we will once again be working with Continental Electric. Several minor details, etc. are still being worked out, but hopefully construction can begin shortly, as the cabinets themselves are slated to arrive late this week or early next week. This should resolve the issue, for at least a several months, of colocation and dedicated server shortages.