Skip to main content
  • Industry Solutions
    • Managed Service Providers
    • Enterprise Solutions
    • Developers & Startups
    • Healthcare
    • Trading and Financial
      • Chicago Managed Trading Servers
      • Trading and Financial Colocation: Chicago & New Jersey
    • IBM AS/400 and iSeries Users
  • Support
    • Register
    • View Tickets
    • Submit a Ticket
    • Knowledgebase
    • News
  • Steadfast Blog
  • Steadfast Podcasts
  • Contact Us
Home
  • Call Us
  • Call | 888.281.9449
  • Login
  • Search

This form logs you into your management portal account. To access your help desk account, click here and use the form to the right of the news.

  • Cloud Hosting
    • Cloud Hosting
    • Private Cloud
    • Hybrid Cloud
    • Public Cloud
    • Cloud Storage
      • Secure File Share
      • Wasabi Cloud Storage
    • Virtual Data Center Platform
  • Managed Hosting
    • Bare Metal Dedicated Servers
      • Deep Learning GPU Dedicated Servers
      • Linux Dedicated Servers
      • Windows Dedicated Servers
    • Virtual Private Servers
    • Data Center Colocation
      • Managed Colocation
      • Chicago: 350 E Cermak
      • Chicago: 725 S Wells
      • Edison, New Jersey
    • Security & Compliance
      • Managed Firewall
      • SSL VPN
      • DDoS Protection
      • Email Security
  • Backup & Disaster Recovery
    • Backup
    • Disaster Recovery
    • Veeam Backup & Replication
    • Veeam Cloud Connect
    • Wasabi Cloud Storage
  • Why Steadfast
    • Why Steadfast?
    • About Steadfast
      • Our History
      • News and Press
    • Data Centers & Network
      • Our Data Centers
      • Our Network
      • Network Test
      • Peering Policy
    • Customer Stories
    • Service Level Agreement
  • Industry Solutions
    • Managed Service Providers
    • Enterprise Solutions
    • Developers & Startups
    • Healthcare
    • Trading and Financial
      • Chicago Managed Trading Servers
      • Trading and Financial Colocation: Chicago & New Jersey
    • IBM AS/400 and iSeries Users
  • Support
    • Register
    • View Tickets
    • Submit a Ticket
    • Knowledgebase
    • News
  • Steadfast Blog
  • Steadfast Podcasts
  • Contact Us
Close
Return to All Blog Posts

Data Center Construction Report - March 3

March 5, 2010 in
Our Customers

Things are progressing nicely and looking great. It is definitely looking like a data center now.

General Building:
Dock: Temporary tap gen box installed.
Vertical Risers: Hogan ground boxes installed.
A/C condenser relocation: Condenser lines removed from future ComEd Vault.

Basement Construction Progress Summary:
Existing Electrical Room: Ground to water service in-progress.
Future Elec Room: Hogan Ground box installation in-progress

7th Floor Construction Progress Summary:
Tennant: Moved misc. equipment into 7th floor storage area.
Doors: Complete except card readers and elec. strikes.
Floors: Complete. Tile trim req. at suite door.
Voice/Data Security: Card reader and elec. strikes req.
Mechanical (Chilled water): Ready to core down to 6th floor.

8th Floor Construction Progress Summary:
Walls: Soffits at water cooler and IDF room near complete.
Doors/Windows: Rear window removed and readied for CRAH unit delivery.
Floors: Raised access floor primarily complete. Stairs primarily complete, awaiting handrails.
Ceilings: Uni-strut installation near complete.
Voice/Data Security: Installation of blue color pipe for Steadfast security and yellow for data in-progress.
Electrical: Wiring in-progress, PDUs arrived and set on stands.
Plumbing: Drain pan installed under overhead lines.
Fire Alarm: Fire alarm control panel installed.
Mechanical (Chilled water): Mech Room primarily complete, small lines left.
Mechanical (Vent): Office mech system near complete, humidistat install in-progress.
Sprinklers: Awaiting ceiling. Total Pac arrived.
Finishes: Primer and first coat paint complete.
Freight Elevator: Elevator cab, frame and curb raised and back in-service.
Miscellaneous: Interior roof steel installed for AHU-A.

Roof Construction Progress Summary:
Exterior: Exhaust fan and piping cores penetrations complete.
Interior: Elec room – 2 hr partitions complete awaiting door.
Elec: Ground box installed.

Share This
facebook twitter email compact

Comments (0)

Leave a Comment

Get an image next to your comment by visiting Gravatar.com and uploading a profile photo that links to your address.

Search the Blog

Categories

backup
(1)
bare metal
(1)
Business Talk
(23)
Chicago
(11)
Chicago colocation
(1)
Cloud
(34)
cloud backup
(1)
cloud services
(4)
colocation
(7)
colocation services
(1)

Archives

  • March 2023 (4)
  • August 2022 (1)
  • March 2022 (3)
  • October 2021 (1)
  • January 2021 (1)
  • July 2020 (1)
  • June 2020 (1)
  • April 2020 (1)
  • March 2020 (1)
  • August 2019 (1)

Follow Us

  • Facebook
  • Twitter
  • LinkedIn
  • RSS Feed
  • 312.602.2689
  • ColoHouse Sales
  • Facebook
  • Twitter
  • YouTube
  • LinkedIn

Services

  • Cloud Hosting
  • Managed Hosting
  • Backup & Disaster Recovery

Solutions By Industry

  • Enterprise Solutions
  • Trading & Financial
  • Healthcare
  • Developers & Startups
© 2023 Steadfast
  • Log In
  • Site Map
  • Legal Info & Privacy Policy