As of Dec. 10 this was the progress:
Basement Construction Progress Summary:
Existing Electrical Room: Temporary C/T Cabinet – installation in progress. Cab is piped to exist switchboard and over to the temporary transformer. Awaiting temp transformer.
7th Floor Construction Progress Summary:
Demolition: Complete.
Walls: Modifications primarily complete awaiting paint.
Doors: New openings framed, awaiting installation
Floors: Preparation for tile started.
Ceilings: New lights being installed and new ceiling tile on-site
8th Floor Construction Progress Summary:
Demolition: Complete.
Walls: Rear (East) windows – blackout film completed.
Floors: Latex coat in progress.
Ceilings: Painting complete.