Skip to main content
  • Industry Solutions
    • Managed Service Providers
    • Enterprise Solutions
    • Developers & Startups
    • Healthcare
    • Trading and Financial
      • Chicago Managed Trading Servers
      • Trading and Financial Colocation: Chicago & New Jersey
    • IBM AS/400 and iSeries Users
  • Support
    • Register
    • View Tickets
    • Submit a Ticket
    • Knowledgebase
    • News
  • Steadfast Blog
  • Steadfast Podcasts
  • Contact Us
Home
  • Call Us
  • Call | 888.281.9449
  • Login
  • Search

This form logs you into your management portal account. To access your help desk account, click here and use the form to the right of the news.

  • Cloud Hosting
    • Cloud Hosting
    • Private Cloud
    • Hybrid Cloud
    • Public Cloud
    • Cloud Storage
      • Secure File Share
      • Wasabi Cloud Storage
    • Virtual Data Center Platform
  • Managed Hosting
    • Bare Metal Dedicated Servers
      • Deep Learning GPU Dedicated Servers
      • Linux Dedicated Servers
      • Windows Dedicated Servers
    • Virtual Private Servers
    • Data Center Colocation
      • Managed Colocation
      • Chicago: 350 E Cermak
      • Chicago: 725 S Wells
      • Edison, New Jersey
    • Security & Compliance
      • Managed Firewall
      • SSL VPN
      • DDoS Protection
      • Email Security
  • Backup & Disaster Recovery
    • Backup
    • Disaster Recovery
    • Veeam Backup & Replication
    • Veeam Cloud Connect
    • Wasabi Cloud Storage
  • Why Steadfast
    • Why Steadfast?
    • About Steadfast
      • Our History
      • News and Press
    • Data Centers & Network
      • Our Data Centers
      • Our Network
      • Network Test
      • Peering Policy
    • Customer Stories
    • Service Level Agreement
  • Industry Solutions
    • Managed Service Providers
    • Enterprise Solutions
    • Developers & Startups
    • Healthcare
    • Trading and Financial
      • Chicago Managed Trading Servers
      • Trading and Financial Colocation: Chicago & New Jersey
    • IBM AS/400 and iSeries Users
  • Support
    • Register
    • View Tickets
    • Submit a Ticket
    • Knowledgebase
    • News
  • Steadfast Blog
  • Steadfast Podcasts
  • Contact Us
Close
Return to All Blog Posts

Data Center Construction Report - April 7

April 9, 2010 in
Our Customers

Things are progressing nicely. The structural steel for the roof mounts for the generator and chiller is being fabricated off-site, thus you can't see it here, but progress is being made. The other major change is that a lot of the UPS gear is now in place, and it is basically just finishing work inside the data center space.

General Building:
Plumbing: New bldg domestic water riser from Basement to 8th Floor installation in-progress.
A/C condenser relocation: Condenser lines removed from future ComEd Vault.

Basement Construction Progress Summary:
Boiler Room: Building stored items primarily removed.
Future Elec Room: Hogan Ground box installation in-progress

6th Floor Construction Progress Summary:
Doors/Windows: Awaiting man doors.
Walls: Completed.
Finishes: Painting complete on walls
Electrical: Further UPS Parallel board conduit installation in-progress. Three
UPS/Battery groups installed. PDU wire pulls to 8th floor complete. Wire pulls to DPRA at penthouse from 6th floor in-progress
Mechanical (Chilled water): Chiller lines complete, awaiting CRAH 5, insulation complete.
Mechanical (Vent): Room exhaust vents and supply vent near complete

7th Floor Construction Progress Summary:
Tennant: Moved misc. equipment into 7th floor storage area.
Floors: Complete. Tile trim req. at suite door.
Voice/Data Security: Wiring of card readers and elec. Strikes in-progress.
Mechanical (Chilled water): Completed.

8th Floor Construction Progress Summary:
Walls: Room walls complete. 8th floor stair walls complete awaiting paint.
Doors/Windows: Door complete.
Floors: Ceramic tile install in-progress at Toilets.
Ceilings: Ceiling tile installation in-progress in Office, Data Room and Toilets
Voice/Data Security: Wire cable tray install in-progress in Data Center, Security
& voice/data cable pull in-progress., Wiring of elec strikes in-progress
Electrical: PDU grounding complete, leak detection at CHRAH units complete.
Plumbing: Awaiting fixtures
Fire Alarm: Fire alarm control panel installed, wiring in-progress.
Mechanical (Chilled water): Piping near complete. Refrigeration piping primarily
complete.
Mechanical (Vent): Duct complete. Awaiting AHU-A install.
Sprinklers: Total Pac piping complete, sprinkler heads complete.
Finishes: Primer and first coat paint complete.
Freight Elevator: Awaiting painting.
Miscellaneous: Window screens replaced
Roof Construction Progress Summary:
Exterior: CU1 & CU2 piping and electric near complete.
Interior: Elec room door completed.
Elec: Conductor pull to DPRA from 6th floor in-progress

Share This
facebook twitter email compact

Comments (0)

Leave a Comment

Get an image next to your comment by visiting Gravatar.com and uploading a profile photo that links to your address.

Search the Blog

Categories

backup
(1)
bare metal
(1)
Business Talk
(23)
Chicago
(11)
Chicago colocation
(1)
Cloud
(34)
cloud backup
(1)
cloud services
(2)
colocation
(4)
colocation services
(1)

Archives

  • August 2022 (1)
  • March 2022 (3)
  • October 2021 (1)
  • January 2021 (1)
  • July 2020 (1)
  • June 2020 (1)
  • April 2020 (1)
  • March 2020 (1)
  • August 2019 (1)
  • July 2019 (1)

Follow Us

  • Facebook
  • Twitter
  • LinkedIn
  • RSS Feed
  • 312.602.2689
  • ColoHouse Sales
  • Facebook
  • Twitter
  • YouTube
  • LinkedIn

Services

  • Cloud Hosting
  • Managed Hosting
  • Backup & Disaster Recovery

Solutions By Industry

  • Enterprise Solutions
  • Trading & Financial
  • Healthcare
  • Developers & Startups
© 2023 Steadfast
  • Log In
  • Site Map
  • Legal Info & Privacy Policy